The expeditious execution of gas power, offshore wind power, and hydrogen projects is contingent upon the competent authorities formulating policies pertaining to these domains.
As it finalises the draft hydrogen production strategy and implements offshore wind power and gas power projects, the Ministry of Industry and Trade (MoIT) will shortly submit a report to the government and present its findings to the appropriate authorities for evaluation.
Offshore wind power, hydrogen, and gas power awaiting policies (source: freepik.com)
Minister of Industry and Trade Nguyen Hong Dien stated at a December 25 meeting that the strategy, which outlines the execution of gas power and offshore wind power projects in accordance with Power Development Plan VIII, has issues surrounding gas power and offshore wind energy initiatives that need to be examined and addressed promptly and simultaneously, from strategies to policy mechanisms.
“Gas power and offshore wind are two crucial energy sources for ensuring national energy security and advancing the energy transition process in Vietnam,” Minister Dien said.
“In addition, the hydrogen development strategy serves as a political orientation and a critical strategy, providing a foundation for the establishment of robust policy mechanisms and facilitating the practical implementation of hydrogen production activities in Vietnam. This not only addresses the demands of the energy transition but also fosters economic progress,” he added.
As stated in a report by the Electricity and Renewable Energy Authority under the MoIT, the execution of gas power and offshore wind power projects in time for commissioning prior to 2030 is a formidable task that demands the involvement of capable authorities and close collaboration among pertinent entities.
Such efforts also serve to safeguard national energy security and facilitate the realisation of Vietnam’s commitment to carbon neutrality.
This report details the investor selection, feasibility study preparation, power purchase contract negotiations, loan arrangement, and execution of engineering, procurement, and construction contracts involved in the execution of gas power projects. The entire process takes approximately 7-8 years.
Pham Van Phong, general director of PetroVietnam Gas (PV Gas), states that the inadequate infrastructure for importing liquefied natural gas (LNG) could impede the advancement of gas power projects and hinder the achievement of objectives outlined in the PDP8.
“The absence of a financial policy, a mechanism to guarantee electricity output coverage, or a mechanism to convert petrol prices to electricity prices in Vietnam have rendered investment projects incapable of ascertaining their capacity to recuperate capital, organising capital, and determining the quantity of LNG imports required to secure competitive petrol prices for electricity production contracts,” said Phong.
Vietnam has a single LNG storage facility at present, according to the general director of PV Gas. PV Gas has successfully concluded and is prepared to supply regasified LNG to consumers in the Southeast region from its import port in the Thi Vai area of the southern province of Ba Ria-Vung Tau, Phong added.
“Other port terminals, such as those situated in import ports that are slated to be incorporated into LNG thermal power initiatives, are confronted with a multitude of challenges and concerns. These encompass technical conditions as well as regulatory issues.”
Phong further underscored that neglecting the integration of LNG import infrastructure with power plants would result in suboptimal resource utilisation, diminished investment efficiency, and inefficient use of Vietnam’s seaport resources.
Le Manh Hung, chairman of PetroVietnam, asserted that at present, all domains associated with the PDP8 implementation fall under PetroVietnam’s purview, with the exception of hydrogen. Nevertheless, investors face significant hazards in gas power and offshore wind power due to the absence of appropriate policies. “However, the lack of mechanisms, policies, and planning, as well as the absence of a location and management agency responsible for approving such projects, pose a significant obstacle,” he said.
Experts in energy and economics concur that international obligations must be carried out expeditiously and that policies and work attitudes must be revised accordingly. The integration of hydrogen production strategies, gas power implementation, and offshore wind power initiatives into the broader national energy strategy is imperative.
Van Nguyen
(Vietnam Investment Review)
- HawaExpo 2024 in HCMC to feature 2,500 furniture booths
- Technology solutions key to Hà Nội's wastewater issues
- Trending towards green industrial parks for capital attraction
- Comprehensive strategy needed to ensure water security in Mekong Delta: experts
- Vietnam to have 108 social housing projects with over 47,500 apartments completed in 2024
- Đà Nẵng City leads the nation in environmental protection, Hà Nội in 46th place, HCM City 19th
- PM outlines tasks for environment sector in 2024
- Four key infrastructure projects inaugurated today
- Localities join in efforts to fight plastics pollution
- Hanoi named among world’s top 100 best cities